Kohima, November 14: A team comprising officials from the Northeast Frontier Railway’s Dimapur–Kohima New Railway Line Project, along with representatives of the Government of Nagaland, conducted an inspection of the ongoing railway project on November 14, 2026.
The inspection team included Thsuvisie Phoji, Additional Secretary, Aircell, Government of Nagaland; Myingthungo Ababe Ezung, OSD, Aircell, Transport Department; and A. Pongshi Phom, Advisor to Airway and Railway, Government of Nagaland. Officials from the Northeast Frontier Railway, including Harji Mal Meena, Deputy Chief Engineer, were also present during the inspection.
The team visited various project locations, including Zubza, Piphema, Pherima and Molvom, inspecting proposed railway station sites, tunnel sections, bridges and locations where railway tracks are to be installed. The inspection was aimed at reviewing the progress and assessing the ongoing construction work.
The Dimapur–Kohima railway line project, sanctioned in May 2007, commenced construction during 2015–16. The project covers a total length of 78.42 kilometres, with the completion target set for December 2029.
Speaking to the media, Advisor A. Pongshi Phom stated that the project has achieved 50 per cent physical progress and 45.98 per cent financial progress. The total expenditure incurred up to October 31, 2026, stands at Rs. 7,176.48 crore.
The project comprises 20 tunnels, of which eight have been completed. The longest tunnel measures approximately 6,620 metres (6.62 km). The project also includes emergency escape or auxiliary tunnels to provide an alternative passage during emergencies.
In terms of bridges, the project includes 29 major bridges, of which 15 have been completed, and 151 minor bridges, with 138 completed. The longest bridge, Bridge No. 154, measures 551.60 metres.
The railway line will have eight stations, with four stations at Dhansiri, Dhansiripar, Sukhovi and Molvom already completed. Pherima and Zubza are among the other key station locations under the project, with Molvom serving as an important station.
The inspection team also reviewed the construction of a major bridge measuring approximately 500–600 feet. Officials highlighted the scale and technical challenges involved in constructing tunnels and bridges across the difficult terrain of Nagaland.
Meanwhile, the proposed extension of the railway line from Zubza towards Imphal, Manipur, is also being explored, with survey work and consultations with consultants underway for the future connectivity plan.
The Dimapur–Kohima railway project is considered a significant infrastructure initiative for Nagaland, expected to improve connectivity, transportation and economic opportunities in the region. With the target completion date set for December 2029, the project remains a major step towards strengthening railway connectivity in the Northeast.